Building hardware for Brazil may be received by floor while the factory packs full cartons by model. The crucial link is carton-to-allocation mapping. A delayed remainder carton can otherwise make several floors incomplete.
Ask which floor is installed first and which components must be used together. Identify inner packs and list quantities against outer carton IDs. Flag mixed cartons for focused inspection rather than asking installers to sort from appearance.
A consolidation warehouse may rebuild pallets, so floor allocation should not exist only on the original wrapping. Retain carton identity through the new pallet. Report maximum package weight and handling restrictions even for apparently small hardware.
If early installation needs hinges and fixing plates, sending only full hinge cartons ahead will not help when the plates are in a mixed carton. Split by a usable installation unit or obtain the buyer's approval to wait.
For a late construction sequence change, preserve original carton IDs and update allocation separately. Repack later lots under the new plan. Avoid two lists assigning different contents to the same ID.
Record transport receipt and kit acceptance separately in Brazil. The carrier handover checks packages and visible condition; the project team checks installable sets. Trace a shortage to the relevant box and use before arranging replacement.